NO | DESCRIPTION | COMPLIANCE |
---|---|---|
1 | FLOOR | |
a) | The floor should be even and level and should not be more than 3mm over 1.20m. | |
b) | No hollow sound when tapped on the floor tiles. | |
c) | No paint drips or other stain marks on the floor finishing. | |
d) | No cracks, chippings and visible damages on the floor finishing. | |
e) | Shading and tonality of the floor tiles or timber panels should be consistent. | |
f) | Jointing between floor tiles or timber floor panels should be consistent and been filled properly. | |
2 | WALL | |
a) | Wall should be even and level and not more than 3mm over 1.20m. | |
b) | Wall squareness should not be more than 4mm when measured with L-Square. | |
c) | No hollow sound when tapped with hard object. | |
d) | No paint drip and stain marks on the wall surface. | |
e) | No cracks, chippings, scratches and other visible damages on the wall finishing. | |
f) | Jointing between wall tiles should be consistent and filled properly. | |
g) | No patchiness and different tonality on the wall finishing. | |
3 | CEILING | |
a) | No waviness or roughness on the ceiling surface. | |
b) | No stain marks, finger prints and paint stain on ceiling. | |
c) | Jointing between ceiling boards and ceiling tee should be consistent. | |
d) | Alignment and levelness of the ceiling should be even and level. | |
e) | No chippings, holes, cracks and other visible damages should be seen on the ceiling surface. | |
4 | DOOR | |
a) | Door frame & door panel should be aligned and leveled. | |
b) | Gap between door frame and wall should be consistent. | |
c) | No dents, cracks, stain marks and other visible damages on the door panels and door frame. | |
d) | All the accessories such as hinges, knob, door stopper, door closer and etc should be in good condition with no stain marks or malfunction. | |
e) | Door should be able to be opened and closed smoothly with no squeaky sound. | |
f) | All the screws and accessories should be installed properly. | |
g) | Door panel should be flush with door frame. | |
h) | No missing accessories. | |
5 | WINDOW | |
a) | Window frame & panel should be aligned and leveled. | |
b) | Gap between window frame and wall should be consistent. | |
c) | Sealant around the window frame should be neat and consistent. | |
d) | No dents, scratches, stain marks and other visible damages on the aluminium frame and glazing. | |
e) | All the accessories such as window stay, handles and screws should be in good condition with no stain mark or malfunction. | |
f) | Window should be able to be opened and closed smoothly with no squeaky sound heard. | |
g) | No sign of water mark or water seepage should be seen. | |
h) | Gasket/rubber of the window should be installed properly. | |
i) | No missing accessories. | |
6 | COMPONENTS (permanent fixture that is fixed into the unit, such as wardrobe, kitchen cabinet, vanity top, wash basin and etc) | |
a) | Component installed should be aligned and leveled. | |
b) | Gap around the components should be consistent and neatly filled. | |
c) | No stain marks, dents, scratches and other visible damages should be seen on the components. | |
d) | All the accessories should be in good condition with no stain mark or malfunction. | |
e) | Components should be functional and can be opened and closed smoothly with no squeaky sound. | |
f) | No missing accessories. | |
7 | M&E FITTING | |
a) | Joint around the fittings should be consistent. | |
b) | Inconsistent joint should be filled / sealed. | |
c) | Spacing between fittings should be consistent. | |
d) | M&E fittings installed should be aligned and leveled. | |
e) | No stain marks, scratches and other visible damages on the fittings. | |
f) | Fittings should be functional. | |
g) | No missing accessories. |